Scrum Pattern: Granularity Gradient

 

  
ContextThe Product Owner has created Product Backlog Items for the a release.
ProblemWhen do which Product Backlog Items need to be broken down?

Decomposing all Product Backlog Items for estimation and realization in a Sprint for a complete release creates wasted effort as requirements change and new requirements arise. Furthermore, estimations are not precise if the Product Backlog Items are realized far in the future.

Forcestoo little/too much effort wasted
too little/too much detail planning
SolutionDecompose Product Backlog Items depending on their realization date.

Break down and estimate Product Backlog Items which will be realized in the next few Sprints and use Themes and Epics for requirements, which are far away. Themes are medium-sized, but too large to be implemented in a single Sprint, Epics can even span multiple Releases.

Although estimates of Themes and Epics are not as precise as estimates of small Product Backlog Items, the effort of breaking them down immediately is wasted in many cases. Furthermore, too many Product Backlog Items clutter the Backlog.

Resulting ContextThe Product Backlog Items have been broken down efficiently.