| Context | The Team coordinates work by Daily Scrums. |
| Problem | What is the best way to report the status of a Sprint? |
| Forces | too little/too much reporting |
| Solution | Maintain a Sprint Burndown Chart. A Sprint Burndown Charts shows remaining work vs. time. Remaining work is shown in the unit used for estimation by the Team. Whereas traditional project reporting provides a lot of information on a weekly or monthly basis with questionable relevance, a Sprint Burndown Chart boils down the most important information into a single chart which is updated daily. |
| Resulting Context | The Scrum Team knows its progress. |